Evaluation and Optimization of Time Management for the Construction Project of Kedang Ipil Water Supply System (SPAM) with a Capacity of 30 Liters per Second in Kota Bangun Darat District Using the Critical Path Method (CPM)

  • Ilja Budi Irawan Universitas 17 Agustus 1945 Samarinda
  • Benny Mochtar Effendi Arifin Universitas 17 Agustus 1945 Samarinda
  • Alpian Nur Universitas 17 Agustus 1945 Samarinda
Keywords: Critical Path, Critical Path Method (CPM), Project Control, SPAM Project, S-Curve, Time Deviation, Time Management

Abstract

Time management in construction projects is one of the key factors determining project success, particularly in complex public infrastructure projects such as the construction of a Drinking Water Supply System (SPAM). This study aims to evaluate the time management of the Kedang Ipil SPAM construction project with a capacity of 30 liters per second in Kota Bangun Darat, Kutai Kartanegara, using the Critical Path Method (CPM). The research data include the planning schedule (time schedule), weekly and monthly realization reports, progress documentation, and work activity weightings. A quantitative descriptive method was used to analyze the critical path, compare planned and actual durations, and evaluate the cumulative progress deviations of the project. The study found that the actual project duration reached 204 days, exceeding the planned duration of 184 days, with a total deviation of 20 days. The identified critical path included key activities such as the construction of the pump house, reservoir, mechanical and electrical installation, and the water treatment plant (WTP). Project delays were caused by issues related to material procurement, adverse weather conditions, and insufficient field coordination. The cumulative progress S-curve analysis showed the largest negative deviation of -4.527% in week 8 and the maximum positive deviation of +4.606% in week 20. Despite the delays, the project managed to achieve 100% cumulative progress by week 24 through efforts such as increasing the workforce, accelerating material procurement, and strengthening field supervision. The implementation of CPM proved effective in detecting critical activities and supporting swift decision-making to minimize delays. These research findings highlight the importance of adaptive and scientifically-based time control in large-scale construction projects and provide practical contributions to the development of time management strategies in similar infrastructure projects.

References

Bhatta, R., Loc, H. H., Babel, M. S., & Chapagain, K. (2024). Assessment and Enhancement of Community Water Supply System Sustainability: A Dual Framework Approach. Enviromental and Sustainability Indicators, 24(100486). https://doi.org/10.1016/j.indic.2024.100486

Gamage, A. (2022). Importance of Effective Communication to Minimize Disputes in Construction Projects. Scholars Journal of Engineering and Technology, 10(07), 128–140. https://doi.org/10.36347/sjet.2022.v10i07.002

Gould, F. E., & Joyce, N. E. (2009). Construction project management (4th ed.). Pearson Education.

Hamid, A. R. A., & Chin, L. S. (2015). The Practice of Time Management on Construction Project. The 5th International Conference of Euro Asia Civil Engineering Forum (EACEF-5). https://doi.org/10.1016/j.proeng.2015.11.006

Heagney, J. (2016). Fundamentals of project management (5th ed.). AMACOM.

Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). John Wiley & Sons.

Larson, E. W., & Gray, C. F. (2017). Project management: The managerial process (7th ed.). McGraw-Hill Education.

Lewis, J. P. (2007). Fundamentals of project management (3rd ed.). AMACOM.

Lock, D. (2020). Project management (11th ed.). Routledge.

Meredith, J. R., & Mantel, S. J. (2012). Project management: A managerial approach (8th ed.). John Wiley & Sons.

Ningsih, A., Surahman, S., Aisyiah, S. A., Syahara, A., & Bayhaqi, A. (2025). Implementation of Critical Path Method (CPM) in Project Management of Type 45 House Construction in Samarinda. Journal of Business Management and Economic Development, 3(02), 758–770. https://doi.org/10.59653/jbmed.v3i02.1657

Pinto, J. K. (2013). Project management: Achieving competitive advantage (3rd ed.). Pearson Education.

PMI (Project Management Institute). (2017). A guide to the project management body of knowledge (PMBOK® guide) (6th ed.). PMI.

PMI (Project Management Institute). (2021). A guide to the project management body of knowledge (PMBOK® guide) (7th ed.). PMI.

Santoso, F. W., Handayani, F. S., & Setiono. (2025). A Comparative Analysis of the CPM and PERT Methods in Project Time Management for a High-Rise Building Construction Project in Yogyakarta. Sustainable Civil Buillding Management and Engineering Journal, 2(2), 1–13. https://doi.org/10.47134/scbmej.v2i2.3927

Sears, S. K., Sears, G. A., & Clough, R. H. (2015). Construction project management: A practical guide to field construction management (6th ed.). Wiley

Published
2025-08-30
Section
Articles